EIA Notification, 2006 Issued on 14.09.2006
OBJECTIVES
To formulate a transparent, decentralized and efficient regulatory mechanism to:
Incorporate necessary environmental safeguards at planning stage
Involve stakeholders in the public consultation process
Identify developmental projects based on impact potential instead of the investment criteria
DEVELOPMENTAL ACTIVITIES REQUIRING ‘EC’
• All new projects/activities listed in Schedule;
• Expansion and/or modernization of existing projects /activities; and
• Change in product mix
DIFFERENCES BETWEEN EIA NOTIFICATION, 1994 & 2006
No NOC for EC
• Revised Schedule based on potential impacts instead of investment criteria
• Categorization into A and B1 & B2
• Category A at Central level, Category B1, B2 at State Level (with exceptions),
• Check-list information in Form-1/Form-1-A
• Scoping to determine TORs for EIA, if required;
• Finality of TORs
• Scoping stage incorporate site clearance – No separate site clearance is required.
• Public consultation structured; To be conducted by SPCB
and presided by DM (with in 45 days); proceedings to be
videographed; MoEF to intervene if PH not held in time
• Time limits with consequences at each stage
• State Level Environment Impact Assessment Authority
(SEIAA), Expert Appraisal Committees (EAC) – Notification
defines qualifications/experience in Appendix-VI